| Project Name | Site Address | Strut Spacing |
Stru Length |
Excavation Depth |
Contractor | Year of Completion |
|---|---|---|---|---|---|---|
| Gajaeul Educational & Research Facility Construction Project | 17 Gajaeulmirai-ro, Seodaemun-gu, Seoul, Korea | 5.0m | 25.5m | G.L-6.76m | The Mir Construction | 2020 |
| Seongsu-dong Mixed-Use Development Project | 11 Achasan-ro 13-gil, Seongdong-gu, Seoul, Korea | 4.5m | 37.1m | G.L-21.30m | Yojin Construction & Development | 2020 |
| KM Tower Construction Project, Gasan-dong, Geumcheon-gu | 95 Gasan Digital 2-ro, Geumcheon-gu, Seoul, Korea | 5.0m | 29.5m | G.L-19.91m | Kangsan Construction | 2020 |
| Semishield (Launch Shaft) for By-product Combined Cycle Power Plant, Pohang | 6262 Donghaean-ro, Nam-gu, Pohang-si, Gyeongsangbuk-do, Korea | 4.7m | 4.3m | G.L-8.96m | POSCO E&C | 2020 |
| Relocation of Metropolitan Water Pipeline for Anseong–Guri Expressway Project | 195 Seohananam-ro, Hanam-si, Gyeonggi-do, Korea | 7.0m | 10.2m | G.L-5.90m | Koryo Development | 2020 |
| Construction of Site Cafeteria for POSCO Project | 6262 Donghaean-ro, Nam-gu, Pohang-si, Gyeongsangbuk-do, Korea | 5.0m | 25.5m | G.L-6.70m | POSCO E&C | 2020 |
| Hangdong 7-ga 31-4 Logistics Center Construction Project, Incheon | 20 Chukhang-daero 165beon-gil, Jung-gu, Incheon, Korea | 4.8m | 39.8m | G.L-9.40m | DL Construction | 2020 |
| Changwon Used Car Complex Construction Project | 79 Mueok-ro, Masanhoewon-gu, Changwon-si, Gyeongsangnam-do, Korea | 5.5m | 93.4m | G.L-9.45m | DL Construction | 2020 |
| Construction of Discharge Outlet for By-product Gas Combined Cycle Power Plant, Pohang | 6262 Donghaean-ro, Nam-gu, Pohang-si, Gyeongsangbuk-do, Korea | 4.5m | 14.1m | G.L-6.85m | POSCO E&C | 2020 |
| Construction of Pumping Station for By-product Gas Combined Cycle Power Plant, Pohang | 6262 Donghaean-ro, Nam-gu, Pohang-si, Gyeongsangbuk-do, Korea | 5.0m | 17.3m | G.L-8.35m | POSCO E&C | 2020 |